Barnard Street Reconstruction

The contractor plans to complete the storm sewer work by Friday, 8-21-09. 
Concrete curb work will be Monday, 8-24-09.

 

The contactor is accommodating residents who need to access their driveways for “move-in”.

 


College Avenue Streetlight Project

During the week of 9/8, Borough crews will be working on restoring the sidewalk/handicapped ramps at the following locations:

 

Garner Street (east side)

Pugh Street (east side)

Crews will also replace a streetlight foundation at McAllister Street.


Street & Alley Resurfacing

S. Allen St.

Foster Ave. to Irvin Ave.

E. Hamilton Ave.

Locust Lane to Hetzel St.

Storch Road

S. Sparks St. to Cul-de-Sac

Berry Alley

Foster Ave. to Irvin Ave.

Apple Alley

E. Fairmount to E. Prospect

Chestnut Alley

Apple Alley to Berry Alley

D Alley

Foster Ave to Highland Alley












From the latest contractor’s schedule {weather pending}:

 

Mill streets & alleys – 9/8 through 9/11

Paving of alleys & Hamilton – 9/14-9/16

Paving Storch Road and Allen Street – 9/16-9/18